Vale Verde and Appian report first blast at Serrote

As copper plunges, Appian bets on shortages from electrification

The Serrote project in Alagoas, Brazil. Image from MVV.

Minera莽茫o Vale Verde and Appian Capital Advisory on Tuesday the first blast at the Serrote copper-gold project in Alagoas, Brazil.

According to Appian, the pre-stripping program has now handled over one million tonnes of material. Construction and engineering works are progressing to plan, with start-up expected in H2 2021.

Based on definitive feasibility study (鈥淒FS鈥), Serrote will require $250 million in capital for a conventional, low-strip open-pit operation targeted to produce 20,000 tonnes of copper equivalent per year over 14 years.

鈥淪errote continues to demonstrate robust economics with potential upside, and we are seeing strong interest from offtake and financing partners,鈥 said Paulo Castellari, CEO, Vale Verde & Appian Brazil.