apk

Site icon apk

Rio Tinto disputes report that mismanagement caused Oyu Tolgoi’s woes

Rio Tinto to write off $2.3bn Oyu Tolgoi loan to Mongolia

Oyu Tolgoi open pit has been producing since 2012. (Image courtesy of )

Rio Tinto(ASX, LON, NYSE: RIO)is challengingthe findings of anindependent reviewinto$1.4 billion in cost overrunsand delaysat the Oyu Tolgoi mine in Mongolia,restating theproject’s troubles were caused byunpredictablegeology issues.

The Independent Consulting Group’s(IGG)reportconcluded last monththat poor management was themainreason themine’sunderground expansionhas run into problems affecting its cost andtimeline.

WhileRiohas said itunderstandsstakeholders’ frustration itbelievesthereviewdid not sufficientlyrecognizethe full impact ofweaker than expected rock conditions, whichforcedthe mining gianttoredesignthe project.

Rio said it understands stakeholders’ frustration, but believes the impact of rock conditions and labour issues on the project’s delays and cost have not been fully recognized

Costs to expand the Oyu Tolgoi mine, Rio’s biggest copper growth project, have ballooned up to $6.75 billion from Rio’soriginal budget of $5.3 billion set in 2016, and this led tofriction over fundingwithmine operator Turquoise Hill (TSX, NYSE: TRQ).The firms finallyreachedan agreement in April.

Canada’sTurquoise Hill, in which Rio has a 50.8% stake, owns 66% of Oyu Tolgoi. The rest is held by the Mongolian government.

“We are concerned that the report takes a narrow view of what constitutes geotechnical impacts on the project,”Rio’s head of projects Mark Davies said in a letter to Mongolia’s justice minister Khishgee Nyambaatar,

Themessage, sent last week,said other issues, such asfitting out a key access shaft,hadalsoaffected the project. It added those matterswere “transparently reported” to its partners.

Davies saidthe fact that 96%of theworkforce was Mongolian, which is“far higher”thaninitially plannedalso weighed on the project,.

“The investment in the national workforce did have an impact on project costs and schedule; more than the ICGrecognizes,” the letter said.

Rio Tinto has repeatedly said the underground expansionof Oyu Tolgoiis its most important growth project.First production,initiallyscheduled forlate 2020,is now expected inOctober 2022.

Once completed, the mine’s underground section will lift production from 125,000–150,000tonnesin 2019 to 560,000tonnesat peak output, which is now expected by 2025 at the earliest. This would make it the biggest new copper mine to come on stream in several years.

Financialregulators in the UKandUSare alsoexamining Rio’s disclosuresabout the delays.

Exit mobile version